Clearwater is Producing Our Own Energy with a 154kW Solar Array

Clearwater Industries has gone solar! In the final quarter of 2023, we replaced our roof and installed a 154kW solar array to support our environmental stewardship. Becoming energy-independent is one step of many in our commitment to the environment [...]

2024-02-19T16:40:02+00:00January 23rd, 2024|Announcements|Comments Off on Clearwater is Producing Our Own Energy with a 154kW Solar Array

We’re Highlighting DAF Systems and Membrane Bioreactors at Process Expo 2023

We're highlighting our dissolved air flotation (DAF) systems, membrane bioreactors (MBR), and moving bed biofilm (MBBR) systems as part of our SigmaDAF USA line at Process Expo in Chicago October 23-25, 2023. Join us at booth #3201 to learn [...]

2023-11-17T15:22:38+00:00October 7th, 2023|Announcements|Comments Off on We’re Highlighting DAF Systems and Membrane Bioreactors at Process Expo 2023

Sand & Gravel Producer Decreases Settling Pond Footprint and Cleaning Time with Coagulant and Flocculant Dosing

Company: Knife River Location: Boise, Idaho Challenge: Remove solids and unwanted fines from process water for reuse. Reduce settling pond footprint. Decrease pond cleaning time. Treatment: Coagulation and flocculation in settling pond. Capacity: 1,600 GPM Unit Type: LQ50 Liquid [...]

2023-10-30T15:31:54+00:00January 26th, 2023|Case Studies, Polymer Systems|Comments Off on Sand & Gravel Producer Decreases Settling Pond Footprint and Cleaning Time with Coagulant and Flocculant Dosing

A Limestone Quarry Eliminates Settling Pond to Access Reserve Deposits with a Closed-Loop Clarification System

Company: Glasgow, Inc. Location: King of Prussia, Pennsylvania, USA Challenge: Eliminate settling pond to access material. Return clarified process water for reuse. Treatment: Flocculation & High Compaction Clarifying Thickener Capacity: 1,800 GPM Unit Type: Sump & Slurry Pumps, LQ50, [...]

2023-09-20T18:42:16+00:00June 25th, 2022|Case Studies, Stationary Clarifier Case Studies|Comments Off on A Limestone Quarry Eliminates Settling Pond to Access Reserve Deposits with a Closed-Loop Clarification System

Installation of a DAF Clarifier as Part of an FBR Process for the Treatment of Wastewater from the Meat Industry

Year: 2019 Project Location: Cárnicas Medina Facility - Valencia, Spain Objectives: Installation of a secondary clarification system to the existing biological treatment, forming a FBR process to comply with the discharge limits. Installed Technologies: In-line coagulation-flocculation tubes SIGMA PFL-180; clarification [...]

2023-09-20T17:43:48+00:00June 18th, 2022|Case Studies, DAF Case Studies|Comments Off on Installation of a DAF Clarifier as Part of an FBR Process for the Treatment of Wastewater from the Meat Industry

Aggregate Producer Eliminates Need for Settling Ponds with Clarifying Thickener and Polymer System

Client: Tri-County Paving, Inc. Location: Arlington, Wisconsin, USA Challenge: Eliminate settling pond, Increase uptime Treatment: Flocculation & High Compaction Clarifying Thickener Capacity: 1,100 GPM Unit Type: M500PP, AutoFloc Dosing System, CW1400HC Results: 64% w/w mud, 95% clean water for [...]

2023-11-17T15:19:03+00:00May 4th, 2022|Case Studies, Stationary Clarifier Case Studies|Comments Off on Aggregate Producer Eliminates Need for Settling Ponds with Clarifying Thickener and Polymer System

Settling on Sustainability

Cleaning out the settling pond and hauling away the muck was a labor-intensive, season-long drain on the bottom line for Wissota Sand & Gravel – one that owner Christopher Larson was no longer willing to settle for. As such, [...]

2023-12-05T21:43:28+00:00May 3rd, 2022|Articles, Stationary Clarifier Case Studies|Comments Off on Settling on Sustainability

Settling Suspended Solids

The discharge of dirty water from wet screens, sand screws or classifiers has always presented numerous challenges to sand washing operations. While the use of settling ponds is typical, the method unleashes a host of disadvantages. Pond maintenance [...]

2023-11-28T21:59:48+00:00May 3rd, 2022|Articles, Stationary Clarifier Case Studies|Comments Off on Settling Suspended Solids

Complete Wastewater Treatment for a Vegetable Processor with RANC & FBR

Year: 2016 Project Location: Congelados de Navarra in Fustiñana, Navarra, Spain. Objectives: Installation of a wastewater treatment plant that allows compliance with the discharge requirements for a vegetable processing facility. The treatment plant must be flexible and adaptable to [...]

2023-09-20T19:43:04+00:00May 3rd, 2022|Case Studies, DAF Case Studies|Comments Off on Complete Wastewater Treatment for a Vegetable Processor with RANC & FBR