Stationary Clarifier Case Studies

A Limestone Quarry Eliminates Settling Pond to Access Reserve Deposits with a Closed-Loop Clarification System

Company: Glasgow, Inc. Location: King of Prussia, Pennsylvania, USA Challenge: Eliminate settling pond to access material. Return clarified process water for reuse. Treatment: Flocculation & High Compaction Clarifying Thickener Capacity: 1,800 GPM Unit Type: Sump & Slurry Pumps, LQ50, [...]

2023-09-20T18:42:16+00:00June 25th, 2022|Case Studies, Stationary Clarifier Case Studies|Comments Off on A Limestone Quarry Eliminates Settling Pond to Access Reserve Deposits with a Closed-Loop Clarification System

Aggregate Producer Eliminates Need for Settling Ponds with Clarifying Thickener and Polymer System

Client: Tri-County Paving, Inc. Location: Arlington, Wisconsin, USA Challenge: Eliminate settling pond, Increase uptime Treatment: Flocculation & High Compaction Clarifying Thickener Capacity: 1,100 GPM Unit Type: M500PP, AutoFloc Dosing System, CW1400HC Results: 64% w/w mud, 95% clean water for [...]

2023-11-17T15:19:03+00:00May 4th, 2022|Case Studies, Stationary Clarifier Case Studies|Comments Off on Aggregate Producer Eliminates Need for Settling Ponds with Clarifying Thickener and Polymer System

Settling on Sustainability

Cleaning out the settling pond and hauling away the muck was a labor-intensive, season-long drain on the bottom line for Wissota Sand & Gravel – one that owner Christopher Larson was no longer willing to settle for. As such, [...]

2023-12-05T21:43:28+00:00May 3rd, 2022|Articles, Stationary Clarifier Case Studies|Comments Off on Settling on Sustainability

Settling Suspended Solids

The discharge of dirty water from wet screens, sand screws or classifiers has always presented numerous challenges to sand washing operations. While the use of settling ponds is typical, the method unleashes a host of disadvantages. Pond maintenance [...]

2023-11-28T21:59:48+00:00May 3rd, 2022|Articles, Stationary Clarifier Case Studies|Comments Off on Settling Suspended Solids

Clarifiers Maximize Geotextile Tube Efficiency

Mechanical dewatering in dredged material management is on the rise. Driving the trend are issues such as high contaminated sediment transportation costs and low space availability at many confined disposal facilities. Clarifiers, or what the industry terms as “thickeners,” [...]

2023-09-20T17:40:03+00:00April 21st, 2022|Articles, Stationary Clarifier Case Studies|Comments Off on Clarifiers Maximize Geotextile Tube Efficiency